Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field
Measurement and Testing Works (Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental
permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,Fep-05/356/2009,
Fep-06/356/2009 and FEP-07/356/2009 Monthly Environmental Monitoring & Audit Report
- March 2014 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
April 2014 |
|
|
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2012/08
Table 3.14 Summary of submission status
under EP-356/2009 and FEP-06/356/2009 Condition
Table 3.15 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2010/08
Table 3.16 Summary of submission status under EP-356/2009 and FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table
5.7 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.11 Water Monitoring Stations for contracts
with respect to remaining DP3
work
areas after the completion of DP5 & DP6 in 2012 and intake diversion in
2013
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.24 Details
of Waste Disposal for Contract no. HK/2012/08
Table 5.25 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
6.2 Summary for Notification of
Exceedance
Appendix 10.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Stage 1 tunnel excavation work to -5.5 mPD
including ELS works for 2nd layer. Bay 5 and Bay 6 blinding layers.
¡P
Ground treatment works and guide wall construction
at the promenade deck area after demolition of the existing pump house.
¡P
Installation of pre-bored H-piles.
¡P
The construction of Dwall at C1/C2 interface and
CSD for pipe pile wall P2 in Area 8.. Plant demobilization. All silos and
plants for previous Dwall construction.
¡P
Road diversion works for the construction of
temporary road at
¡P
Cooling mainlaying works for BI, BG & BF. Works
at
¡P
Salt watermain laying works for S8B along
¡P
Sewer works near the junction of
¡P
Remedial works and tree transplanting at Tsim Sha
Tsui site B (near
Section III
¡P
Installation of steel post for the proposed covered
walkway was commenced on 13 Mar 14.
¡P
Modification of road junction between
Sections IVA, IVB & IVC
¡P
The wall and top slab of 8x8 pit. The backfilling work together with the
shaft construction.
¡P
P7, P8 & P9 Cooling Water Pumping Stations was
handed over to the Owner.
¡P
The cable relocation for cooling water pumping
station.
Section V
¡P
Replacement the defected gasket for the DN800
collar joint.
¡P
Commissioning of the new Salt Water Intake System.
¡P
WSD Salt Water Pumping Station was handed over to
WSD.
¡P
Removal of DN600 temporary discharge pipe.
¡P
Installation of Boundary wall and the main gate
installation.
¡P
Defect rectification works and other outstanding
ABWF Works in WSD Salt Water Pumping Station.
Section VII:
¡P
The finial pour of manhole MH2.
¡P
CCTV inspection between manhole MH2 and SLO-03,
SLO-03 and drain outlet of DN1050 drain.
¡P
Reinstatement of existing manhole up to top slab at
the upstream of Box Culvert N1.
Section VIIIA:
¡P
Fire services fresh watermains to Ferry Pier was
connected and certified by WSD.
¡P
2nd Fire Service Department Inspection was carried
out on and had to be followed up as requested by FSD.
¡P
T&C of Movable Ramp.
¡P
At Observation Deck Level, re-installation the
glass of disabled lift and the scaffolding erection for roof canopy cladding
installation. Installation of roof canopy cladding, tempered glass balustrade,
seating base plates and steel frames, and tiling to planter walls.
Section XI:
WCR4/TWCR4 Reclamation:
¡P
Further reclamation to WCR4/TWCR4
by derrick barge.
Work related to HHR Flyover
Diversion (Stage 2):
¡P
All 21 nos. mini-piling works for the foundation of
Bridge 3.
¡P
The loading test of M7 mini-pile. Kentledge
dismantling.
¡P
Excavation to pile cap level of mini-piles.
¡P
Welding for the steel plate on mini-pile heads.
¡P
Construction of EVA
¡P
Removal of marine platform
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Installation of dewatering well
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building
¡P
ELS for box culvert La at
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Works for abandoning submarine sewerage outfall and
watermain
¡P
Installation of caisson seawall unit
Noise
Monitoring
Real-time
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
||
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
HK/2009/02 Monitoring started
on |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Monitoring started
on |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 &
HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
5 |
0 |
1 |
Remarks: - The cessation of seawater
intake operation for C6 was confirmed on
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on
- C8 and C9 were implemented with
respect to HY/2009/19 from
- C8 & C9 was temporary
suspended on
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since
- C5e and C5w water quality
monitoring station was temporarily suspended since
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
2 |
0 |
2 |
|
Ex-WPCWA SE |
0 |
2 |
0 |
2 |
|
Total |
0 |
4 |
0 |
4 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Diversion of traffic from
¡P
Installation of pre-bored H-piles. Meanwhile in the
reclaimed area in stage 3, plant mobilization (e.g. piling rig) at the area
adjacent to the temp road after road diversion.
¡P
Stage 1 tunnel excavation work further down to -10
mPD. Bay 6 blinding layer. The
¡P
overall Stage 1 tunnel structure works.
¡P
Stage 2 construction of Dwall at Water Channel
south side
¡P
Cooling mainlaying works for BI, BG & BF along
¡P
Trimming works at Fairway and the target.
¡P
Tree transplanting works at Tsim Sha Tsui planter
area near HK Culture Centre.
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
Sections IVA, IVB & IVC:
¡P
All outstanding works for handing over P7, P8 and
P9 Cooling Water Pumping Stations including the 8x8 pit and the adjacent cable
relocation to their permanent location.
Section V:
¡P
Capping the existing DN600 salt watermains at
¡P
All outstanding ABWF works at WSD Salt Water
Pumping Station.
Section VII:
¡P
Backfilling works for
Section VIIIA & VIIIB:
¡P
All plumbing system including the connection with
the existing water supplies system in order to secure the Water Certificate
(WWO46) from WSD.
¡P
ABWF works at 1/F and 2/F of Ferry Pier and ready
for handing over it to Star Ferry for commencing their fitting-out works.
¡P
Installation of fender system.
¡P
Testing & commissioning of both movable ramps and
disabled lift for subsequent handing over to Star Ferry.
¡P
Installation of seating base plates and steel
frames and roof canopy cladding installation.
Section XI:
¡P
Removal of existing E&M equipment at the
abandoned SHK Cooling Water Pump House.
¡P
Advanced dredging works of WCR3 by night work
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
Contract no. HK/2010/06 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
¡P
Removal of marine platform
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building
¡P
U-beam installation
¡P
Parapet
¡P
Wing slab extension for segment
Contract
no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West
¡P
ELS for box culvert La at
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Works for abandoning submarine sewerage outfall
Contract no.
HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)
¡P
Nil
1.1.1. Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit
nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009,
FEP-06/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under Particular Specification Section
27.
1.1.3. This
report documents the finding of EM&A works for Environmental Permit no.
EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 during the
period of January 2014 to February 2014. The cut-off date of reporting is at 27th
of each reporting month.
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. ¡§Wan Chai
Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass
and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and
2.1.2. The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3. There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1. The
Project is located mainly in Wan Chai North,
2.2.2. The study
area encompasses existing developments along the Wan Chai,
2.2.3. The scope of the Project comprises:
¡P
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
¡P
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
¡P
Construction
of the new waterfront promenade, landscape works and the associated utility
services
¡P
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4. The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (Eps) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm and
include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to apply
Further Environmental Permits (FEP) such that the impact monitoring stations
are sub-divided accordingly to facilitate the implementation of EM&A
programme and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2. The
details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
|
DP1, DP2 |
|
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
|
DP1 |
|
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
(Completed) |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
|
DP1 |
|
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
|
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
(Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
|
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
|
HK/2012/08 |
Wan Chai Development
Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
|
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
|
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. Simon Liu |
2162 9909 |
2587 1878 |
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr Kenneth
Chan |
9160 3850 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Frank So |
9863 6587 |
|||
Assistant
Environmental Engineer |
|
6157 7057 |
|||
Environmental
Supervisor |
|
9047 6148 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Alfred Leung |
3658-3022 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractor¡¦s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Andy Mak |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Eric
Yip |
2529 2068 |
|||
Environmental
Officer |
Clement
Pang |
9735 9200 |
|||
Environmental
Supervisor |
Jacky
Cheung |
9779 2292 |
|||
Chun Wo ¡V CRGL ¡V MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
|
Site Agent |
Mr. Eric Yip |
252902068 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leader JV |
Contractor under Contract no. HK/2012/08 |
Project Director |
Andrew Tse |
9137 1811 |
2877 1522 |
Project Manager |
Victor Wu |
9193 8871 |
|||
Deputy Project Manager |
George Cheung |
9268 1918 |
|||
Site Agent |
Paul Lui |
9095 7922 |
|||
Environmental Officer |
James Ma |
9130 9549 |
|||
Environmental Supervisor |
Ching Man, Chan |
6050 4919 |
|||
|
Contractor under
Contract no. HY/2010/08 |
Project Director |
Cheung Kit Cheung |
3557 6399 |
2566 8061 |
|
|
Project Manager |
Chan Ying Lun |
9812 0592 |
|
|
|
Deputy Project Manager |
Chris Leung |
3467 4299 |
|
|
|
Site Agent |
Dave Chan |
3467 4277 |
|
|
|
Environmental Officer |
C.M. Wong |
3557 6464 |
|
|
|
Environmental Supervisor |
Louis Lam Tsz Kwan |
3557 6470 |
|
ENVIRON
Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. For
Contract no. HK/2009/01, the principal work activities in this reporting month
included:
¡P
Stage 1 tunnel excavation work to -5.5 mPD
including ELS works for 2nd layer. Bay 5 and Bay 6 blinding layers.
¡P
Ground treatment works and guide wall construction
at the promenade deck area after demolition of the existing pump house.
¡P
Installation of pre-bored H-piles.
¡P
The construction of Dwall at C1/C2 interface and
CSD for pipe pile wall P2 in Area 8.. Plant demobilization. All silos and
plants for previous Dwall construction.
¡P
Road diversion works for the construction of
temporary road at
¡P
Cooling mainlaying works for BI, BG & BF. Works
at
¡P
Salt watermain laying works for S8B along
¡P
Sewer works near the junction of
¡P
Remedial works and tree transplanting at Tsim Sha
Tsui site B (near
2.4.4. For
Contract no. HK/2009/02, the principal work activities in this reporting month
included:
Section
III
¡P
Installation of steel post for the proposed covered
walkway was commenced on 13 Mar 14.
¡P
Modification of road junction between
Sections
IVA, IVB & IVC
¡P
The wall and top slab of 8x8 pit. The backfilling work together with the
shaft construction.
¡P
P7, P8 & P9 Cooling Water Pumping Stations was
handed over to the Owner.
¡P
The cable relocation for cooling water pumping
station.
Section
V
¡P
Replacement the defected gasket for the DN800
collar joint.
¡P
Commissioning of the new Salt Water Intake System.
¡P
WSD Salt Water Pumping Station was handed over to
WSD.
¡P
Removal of DN600 temporary discharge pipe.
¡P
Installation of Boundary wall and the main gate
installation.
¡P
Defect rectification works and other outstanding
ABWF Works in WSD Salt Water Pumping Station.
Section
VII:
¡P
The finial pour of manhole MH2.
¡P
CCTV inspection between manhole MH2 and SLO-03,
SLO-03 and drain outlet of DN1050 drain.
¡P
Reinstatement of existing manhole up to top slab at
the upstream of Box Culvert N1.
Section
VIIIA:
¡P
Fire services fresh watermains to Ferry Pier was
connected and certified by WSD.
¡P
2nd Fire Service Department Inspection was carried
out on and had to be followed up as requested by FSD.
¡P
T&C of Movable Ramp.
¡P
At Observation Deck Level, re-installation the
glass of disabled lift and the scaffolding erection for roof canopy cladding
installation. Installation of roof canopy cladding, tempered glass balustrade,
seating base plates and steel frames, and tiling to planter walls.
Section
XI:
WCR4/TWCR4 Reclamation:
¡P
Further reclamation to WCR4/TWCR4 by derrick barge.
Work related to HHR Flyover Diversion (Stage 2):
¡P
All 21 nos. mini-piling works for the foundation of
Bridge 3.
¡P
The loading test of M7 mini-pile. Kentledge
dismantling.
¡P
Excavation to pile cap level of mini-piles.
¡P
Welding for the steel plate on mini-pile heads.
2.4.5. For
Contract no. HY/2009/15, the principal work activities in this reporting month
included:
¡P
Construction of EVA
2.4.6. For
Contract no. HK/2010/06, no principal work activities in this reporting month.
2.4.7. For
Contract no. HY/2009/19, the principal work activity in this reporting month
included:
¡P
Removal of strut at ELS
¡P
Removal of marine platform
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Installation of dewatering well
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine
section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building
2.4.8. For Contract no.
HK/2012/08, the principal work activity in this reporting month included:
¡P
ELS for box culvert La at
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Works for abandoning submarine sewerage outfall and
watermain
¡P
Installation of caisson seawall unit
2.4.9. For
Contract no. HY/2010/08, no principal work activities this reporting month.
2.4.10. In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Diversion of traffic from
¡P
Installation of pre-bored H-piles. Meanwhile in the
reclaimed area in stage 3, plant mobilization (e.g. piling rig) at the area adjacent
to the temp road after road diversion.
¡P
Stage 1 tunnel excavation work further down to -10
mPD. Bay 6 blinding layer. The
¡P
overall Stage 1 tunnel structure works.
¡P
Stage 2 construction of Dwall at Water Channel
south side
¡P
Cooling mainlaying works for BI, BG & BF along
¡P
Trimming works at Fairway and the target.
¡P
Tree transplanting works at Tsim Sha Tsui planter
area near HK Culture Centre.
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
Sections
IVA, IVB & IVC:
¡P
All outstanding works for handing over P7, P8 and
P9 Cooling Water Pumping Stations including the 8x8 pit and the adjacent cable
relocation to their permanent location.
Section
V:
¡P
Capping the existing DN600 salt watermains at
¡P
All outstanding ABWF works at WSD Salt Water
Pumping Station .
Section
VII:
¡P
Backfilling works for
Section
VIIIA & VIIIB:
¡P
All plumbing system including the connection with
the existing water supplies system in order to secure the Water Certificate
(WWO46) from WSD.
¡P
ABWF works at 1/F and 2/F of Ferry Pier and ready
for handing over it to Star Ferry for commencing their fitting-out works.
¡P
Installation of fender system.
¡P
Testing & commissioning of both movable ramps and
disabled lift for subsequent handing over to Star Ferry.
¡P
Installation of seating base plates and steel
frames and roof canopy cladding installation.
Section
XI:
¡P
Removal of existing E&M equipment at the
abandoned SHK Cooling Water Pump House.
¡P
Advanced dredging works of WCR3 by night work.
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (
¡P
Construction of EVA
Contract no. HK/2010/06 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
¡P
Removal of strut at ELS
¡P
Removal of marine platform
¡P
Construction of Dolphin Cap
¡P
ELS, EVB and Cut & Cover Tunnel
¡P
Laying of 1500f pipe
¡P
Launching of segments
¡P
Extraction of temporary pile from marine section
¡P
Construction of bridge TA1
¡P
Pre-bored H-pile for Admin. Building
¡P
U-beam installation
¡P
Parapet
¡P
Wing slab extension for segment
Contract no. HK/2012/08 ¡V Wan Chai Development
Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
¡P
ELS for box culvert La at
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Works for abandoning submarine sewerage outfall
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel (Slip Road 8)
¡P
Nil
3.1.1. A summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
|
Valid |
Environmental Permit |
EP-364/2009/A |
|
Superseded |
Environmental Permit |
EP-364/2009/B |
|
Valid |
Environmental Permit |
EP-364/2009 |
|
Superseded |
Environmental Permit |
EP-376/2009 |
|
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
|
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
|
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
|
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
|
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
|
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
|
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
|
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
|
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
|
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
|
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
|
Valid |
Further Environmental Permit |
FEP-07/364/2009/B |
|
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
|
Valid |
Further Environmental Permit |
FEP-06/356/2009 |
|
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
|
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
|
Valid |
3.1.2. Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
3.1.3. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are
shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
|
N/A |
Valid |
FEP-02/364/2009 |
|
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
|
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1063-13 |
|
|
Expired |
|
GW-RE1034-13 |
|
|
Valid |
|
GW-RS1091-13 |
|
|
Valid |
|
GW-RS1094-13 |
|
|
Valid |
|
GW-RS1114-13 |
|
|
Valid |
|
GW-RS1153-13 |
|
|
Cancelled |
|
GW-RS1083-13 |
|
|
Cancelled |
|
GW-RS1211-13 |
|
|
Valid |
|
GW-RS1246-13 |
|
|
Valid |
|
GW-RS1265-13 |
|
|
Valid |
|
GW-RS-1270-13 |
|
|
Valid |
|
GW-RS1324-13 |
|
|
Valid |
|
GW-RS1374-13 |
|
|
Valid |
|
GW-RS1433-13 |
|
|
Valid |
|
GW-RS1450-13 |
|
|
Valid |
|
GW-RS0111-14 |
|
|
Valid |
|
GW-RS0200-14 |
|
|
Valid |
Discharge Licence |
WT00006220-2010 |
|
|
Valid |
WT00009641-2011 |
|
|
Valid |
|
|
WT00018110-2014 |
|
|
Valid |
Billing account under Waste Disposal
Ordinance |
7010069 |
|
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
|
N/A |
Valid |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
|
Condition 2.7 |
Works Schedule and
Location Plan |
|
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev. 5) |
|
Silt Curtain
Deployment Plan (Rev. 4) |
|
|
Silt Curtain
Deployment Plan (Rev. 3) |
|
|
Silt Curtain
Deployment Plan |
|
|
Condition 2.9 |
Silt Screen
Deployment Plan (Rev.5) |
|
Silt Screen
Deployment Plan (Rev.4) |
|
|
Silt Screen
Deployment Plan |
|
|
Conditions 2.8 and
2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
|
Report on Field
Testing for Silt Curtain |
|
|
Report on Field
Testing for Silt Curtain (Rev. A) |
|
|
Condition 2.12(d) |
Alternative
Proposal on Concurrent Dredging for Sewage Pipeline and |
|
Condition 2.17 |
Noise Management
Plan |
|
Condition 2.18 |
Landscape Plan
(Erection of Decorative Screen Hoarding along Construction Site around |
15 May 2010 |
|
Landscape Plan
(Night-time Lighting) |
|
|
Landscape Plan
(Rev. B) |
|
Condition 1.12 |
Notification of
Commencement Date |
|
Condition 2.6 to
2.8 |
Management
Organization, Works Schedule and Location Plan |
18 May 2011 |
Condition 2.9 |
Silt Screen
Deployment Plan |
|
Condition 2.18 |
Landscape Plan |
|
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.4. Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2009/02
under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
FEP-03/356/2009 |
|
N/A |
Valid |
|
|
FEP-01/364/2009 |
|
N/A |
Valid |
Notification of Works Under APCO |
313962 |
|
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0945-13 |
|
|
Valid |
|
GW-RS0993-13 |
|
|
Valid |
|
GW-RS1027-13 |
|
|
Valid |
|
GW-RS1002-13 |
|
|
Valid |
|
GW-RS1078-13 |
|
|
Valid |
|
GW-RS1119-13 |
|
|
Valid |
|
GW-RS1128-13 |
|
|
Valid |
|
GW-RS1197-13 |
|
|
Valid |
|
GW-RS1254-13 |
|
|
Valid |
|
GW-RS1256-13 |
|
|
Valid |
|
GW-RS1240-13 |
|
|
Valid |
|
GW-RE1199-13 |
|
|
Valid |
|
GW-RS1258-13 |
|
|
Valid |
|
GW-RS1261-13 |
|
|
Valid |
|
GW-RS1325-13 |
|
|
Valid |
|
GW-RS1337-13 |
|
|
Valid |
|
GW-RS1466-13 |
|
|
Valid |
|
GW-RS1458-13 |
|
|
Valid |
|
GW-RS0067-14 |
|
|
Valid |
|
GW-RS0112-14 |
|
|
Valid |
|
GW-RS0161-14 |
|
11 Mar 2014 to 10 Sep 2014 |
Valid |
|
GW-RS0162-14 |
|
20 Mar 2014 to 19 Sep 2014 |
Valid |
|
GW-RS0233-14 |
|
25 Mar 2014 to 24 Sep 2014 |
Valid |
|
GW-RS0269-14 |
|
|
Valid |
Discharge Licence |
WT00006249-2010 |
|
|
Valid |
WT00006436-2010 |
|
|
||
WT00006673-2010 |
14 May 2010 |
|
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
|
|
Valid |
|
WT00008982-2011 |
|
|
Valid |
|
WT00009691-2011 |
|
|
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
|
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
|
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
|
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
|
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/14-098 |
|
|
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date
of Construction of Marine Works |
|
Condition 2.6 |
Management
Organization of Main Construction Companies |
|
Condition 2.7 |
Works Schedule and
Location Plans |
|
Condition 2.8 |
Silt Curtain
Deployment Plan (Revision A) |
|
Silt Curtain
Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain
Deployment Plan (Revision C) |
|
|
Silt Curtain
Deployment Plan (Revision H) |
|
|
Silt Curtain
Deployment Plan (Revision I) |
|
|
Silt Curtain
Deployment Plan (Revision J) |
|
|
Silt Curtain
Deployment Plan (Revision K) |
3 May 2012 |
|
Silt Curtain
Deployment Plan (Revision L) |
|
|
Silt Curtain
Deployment Plan (Revision M) |
|
|
Condition 2.9 |
Silt Screen
Deployment Plan |
|
Supplementary
Information for Existing WSD Salt Water Intakes at |
|
|
Silt Screen
Deployment Plan (Revision B) |
|
|
Silt Screen
Deployment Plan (Revision C) |
3 May 2012 |
|
Silt Screen
Deployment Plan (Revision D) |
|
|
Condition 2.17 |
Noise Management
Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan
(Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan
(Control of Night Time Lighting) |
|
|
Landscape Plan
(Combined Version) |
|
|
Landscape Plan
(Combined Version) |
|
|
----- |
Acknowledge of
Submission |
|
Contract no. HY/2009/15 ¡V Central-Wanchai
Bypass ¡V Tunnel (
3.1.5. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are
shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
|
N/A |
Valid |
Notification of Works Under APCO |
321822 |
|
N/A |
Valid |
Construction Noise
Permit (CNP) for concreting works at Eastern Breakwater of CBTS |
GW-RS0095-14 |
|
|
Valid |
Construction Noise
Permit (CNP) for Pre-treatment, ELS and rock breaking works at TS4/ME4 |
GW-RS1437-13 |
|
|
Valid |
Construction Noise
Permit (CNP) for maintenance dredging |
GW-RS1232-13 |
|
|
Valid |
Construction Noise
Permit (CNP) for P3 Mooring |
GW-RS0191-14 |
|
12 Mar 2014 to 11 Sep 2014 |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
|
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
|
|
Valid |
Billing Account under Waste Disposal
Ordinance (Dumping by Vessel) |
7011761 |
|
|
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/14-122 |
|
|
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/14-123 |
|
|
Valid |
Dumping Permit (Type 2 ¡V |
EP/MD/14-141 |
|
|
Expired |
|
EP/MD/14-154 |
|
21 Mar 2014 to 20 Apr 2014 |
Valid |
Dumping Permit (Type 3 ¡V |
EP/MD/14-131 |
|
|
Expired |
|
EP/MD/14-147 |
|
15 Mar 2014 to 14 Apr 2014 |
Valid |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
|
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule and Location Plans |
|
|
Amendment for Works Schedule and Location
Plans |
|
Condition 2.8 |
Silt Curtain Deployment Plan |
|
|
Amendment for Silt Curtain Deployment Plan |
|
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment Plan |
|
|
Amendment for Silt Curtain Deployment Plan |
|
|
Condition 2.9 |
Silt Screen
Deployment Plan |
|
Amendment for Silt Screen Deployment Plan |
|
|
Amendment for Silt Screen Deployment Plan |
|
|
Condition 2.18 |
Proposal
for the Removal of Odorous Sediment and Slime |
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
|
|
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
|
Condition 2.21 |
Landscape Plan |
|
Condition 2.20 |
Noise Management Plan |
|
Amendment for Noise Management Plan |
|
3.1.6. Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 3.1.
Contract no. HK/2010/06 ¡V Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.7. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2010/06 under EP-356/2009 is shown
in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
|
N/A |
Valid |
FEP-08/364//2009/A |
|
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
|
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0030-13 |
|
6 Jan 14 ¡V 5 Jul 14 |
Valid |
Billing Account under Waste Disposal
Ordinance |
7012338 |
|
N/A |
Valid |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date
of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
|
Condition 2.7 |
Works Schedule and Location Plans |
|
Condition 2.8 |
Revised Silt Curtain Deployment Plan |
|
Revised Silt Curtain Deployment Plan |
|
|
Revised Silt Curtain Deployment Plan |
|
|
Revised Silt Curtain Deployment Plan |
|
|
Condition 2.9 |
Silt Screen Deployment Plan |
|
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.8. Summary of
the current status on licences and/or permits on environmental protection
pertinent for contract no. HY/2009/19 is shown in Table 3.12.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/B |
|
Granted |
Valid |
Notification of Works Under APCO |
326160 |
|
Notified |
Valid |
Construction Noise Permit (CNP) (For D-wall
construction) (Portion I, VII, VIII & IX) |
GW-RS1473-13 |
|
|
Cancelled |
|
GW-RS0152-14 |
|
|
GW-RS0152-14 |
Construction Noise Permit (CNP) (For Segment
Launching at Portion III) |
GW-RS1009-13 |
|
|
Cancelled |
|
GW-RS1176-13 |
|
|
Cancelled |
|
GW-RS1474-13 |
|
|
Cancelled |
|
GW-RS0072-14 |
|
|
Valid |
Construction Noise
Permit (CNP) (For IEC Parapet Removal ¡V Loading/Unloading) |
GW-RS1099-13 |
|
|
Valid |
Construction Noise
Permit (CNP) (For Portion Vi Marine) |
GW-RS1179-13 |
|
|
Cancelled |
|
GW-RS10073-14 |
|
|
Valid |
Discharge Licence
(Land) |
WT00010093-2011 |
|
|
Valid |
Discharge Licence (Sea) |
WT00010865-2011 |
|
|
Valid |
C&D Waste Disposal |
7012306 |
|
Registered |
- |
Vessel Disposal |
7013285 |
|
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
|
Registered |
- |
Dumping Permit (Tunnel) (Type 1 ¡V |
EP/MD/14-104 |
|
|
Valid |
|
EP/MD/14-128 |
|
|
Valid |
Dumping Permit (Tunnel) (Type 1 ¡V |
EP/MD/14-127 |
|
|
Expired |
|
EP/MD/14-150 |
|
|
Valid |
Contract no. HK/2012/08 ¡V Wan Chai Development
Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
3.1.9. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2012/08 under EP-356/2009 are
shown in Table 3.13 and Table 3.14.
Table 3.13 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/356/2009 |
|
N/A |
Valid |
Notification of Works Under APCO |
355439 |
|
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
|
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7016883 |
|
|
Valid |
Water Discharge Licence |
WT00018223-2014 |
|
|
Valid |
Construction Noise Permit |
GW-RS1477-13 |
|
|
Cancelled |
|
GW-RS0232-14 |
|
23 Mar 2014 to 20 Sep 2014 |
Valid |
|
GW-RS0824-13 |
|
|
Expired |
|
GW-RS0896-13 |
|
|
Cancelled |
|
GW-RS1175-13 |
|
|
Cancelled |
|
GW-RS01086-13 |
|
|
Expired |
|
GW-RS1231-13 |
|
|
Expired |
|
GW-RS1357-13 |
|
|
Valid |
|
GW-RS0257-14 |
|
28 Mar 2014 to 25 Sep 2014 |
Valid |
|
GW-RS0193-14 |
|
27 Mar 2014 to 26 Sep 2014 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/14-111 |
|
|
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/14-120 |
|
|
Expired |
EP/MD/14-120 |
|
|
Valid |
Table 3.14 Summary
of submission status under EP-356/2009 and FEP-06/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan (Rev. 3) |
Submitted
on 25 Nov 2013 was returned to CSLJV by EPD. |
Condition 2.9 |
Silt Screen Deployment Plan (Rev. 2) |
Generally
in order as commented by EPD on |
Condition 2.23 |
Noise Management Plan (Rev. 2) |
Generally in order as commented by EPD on |
Condition 2.24 |
Landscape Plan (Rev. 3) |
Generally
in order as commented by EPD on |
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel (Slip Road 8)
3.1.10. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2010/08 under EP-356/2009 are
shown in Table 3.15 and Table 3.16.
Table 3.15
Cumulative Summary of Valid Licences and Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-07/356/2009 |
|
NA |
Valid |
|
FEP-10/364/2009/B |
|
NA |
Valid |
Notification of Works Under APCO |
357176 |
|
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
|
NIL |
Valid |
Billing Account under Waste Disposal Ordinance |
7017170 |
|
NIL |
Valid |
Water Discharge Licence |
WT00016561-2013 |
|
|
Valid* |
Dumping Permit (Type 1 ¡V |
EP/MD/14-095 |
|
|
Valid |
Table 3.16 Summary
of submission status under EP-356/2009 and FEP-07/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan |
|
Condition 2.9 |
Silt Screen Deployment Plan |
|
Condition 2.23 |
Noise Management Plan |
|
Condition 2.24 |
Landscape Plan |
|
Noise Monitoring Stations
4.1.1. The noise
monitoring stations for the Project are listed and shown in Table 4.1
and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
|
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring
Stations
4.1.2. The
real-time noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
4.1.3.
The real-time noise monitoring at RTN2-Oil
Street Community Liaison Centre has been relocated to City Garden Electric
Centre (RTN2a- Electric Centre) on
4.1.4. As the
land-based piling and filling works- DP3 at Tin Hau had been completed on
Table 4.2 Real
Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitfield Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.5. The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.6. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.7. If
construction works are extended to include works during the hours of 1900 ¡V
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1. The air
monitoring stations for the Project are listed and shown in Table 4.3 and
Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a ¡V Future
CWB site office at Wanchai Waterfront Promenade and CMA6a ¡V Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
¡P
0.6
¡V 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6. Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7. A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. An alternative non-HOKLAS
accredited laboratory was set-up
for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on
4.2.9. Filter
paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a humidity-controlled
chamber for over 24-hours and be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be
at least 16 years of age;
¡P
be
free from any respiratory illnesses; and
¡P
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
¡P
before
and during odour patrol
4.2.13. Odour patrol
shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 ¡V
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 ¡V
Slight Identifiable odour, and slight chance to have odour nuisance;
¡P
2 ¡V
Moderate Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 ¡V
Strong Identifiable, likely to have odour nuisance;
¡P
4 ¡V
Extreme Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17. The
qualified odour patrol member has individual n-butanol thresholds complied with
the requirement of European Standard Method of Air Quality ¡V Determination of
Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80
ppb.
4.3.1. The EIA
Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water intakes.
The impact monitoring should be carried out during the proposed dredging works
to ensure the compliance with the water quality standards.
4.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on
Water Quality Monitoring Stations
4.3.3. It is proposed
to monitor the water quality at 4 WSD salt water intakes and 8 cooling water
intakes along the seafront of the
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
|
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings ( |
835895.2 |
816215.2 |
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
Water Quality Parameters
4.3.4. Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory.
4.3.5. In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
Sampling Procedures and
Monitoring Equipment
4.3.6. The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table 4.5 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling event.
For selection of tides for in-situ measurement and water sampling, tidal range
of individual flood and ebb tides should be not less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7. The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
use a DC power source. It should be capable of measuring:
¡P
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a
temperature of 0-45 degree Celsius
4.3.8. It should
have a membrane electrode with automatic temperature compensation complete with
a cable. Sufficient stocks of spare electrodes and cables should be available
for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI
5795A submersible stirrer with reel and cable or an approved similar
instrument).
4.3.9. Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and
Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement /
Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth
may be omitted. If the water depth be equal to or less than 3m, only the
mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily
monitoring of suspended solids and 24 hour monitoring of turbidity at the
cooling water intakes (C6 and C7) shall be
conducted.
4.3.25.
The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. The monitoring system include the
turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored.
4.3.27.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1. The
environmental monitoring will be implemented based on the division of works areas
of each designed project managed under different contracts with separate FEP
applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure 2.1 and Figure
4.1. The monitoring results are presented in according to the
Individual Contract(s).
5.0.2. In the
reporting month, the concurrent contracts are as follows:
Contract no. HK/2009/01 ¡V
Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at
Contract no. HK/2009/02 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19-
Cental- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no. HK/2012/08 ¡V
Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
Contract no. HY/2010/08 ¡V
Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
5.0.3. The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.1. The
proposed division of noise monitoring stations are summarized in Table
5.2 below.
Table 5.2 Noise Monitoring Station for Contract nos.
HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.2. Daytime
and evening period noise monitoring was conducted at the Harbour Road Sport
Centre in the reporting month.
5.1.3. No
exceedance was recorded in this reporting
period. Details of
noise monitoring results and graphical presentation can be referred in Appendix
5.2
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.4. The noise
monitoring for HY/2009/15 was commenced on
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
|
M3a |
Tung Lo Wan Fire Station |
5.1.5. Noise
monitoring results measured in the period of daytime and restricted hour are
reviewed and summarized. No exceedance was recorded in this reporting period. Details
of noise monitoring results and graphical presentation can be referred in Appendix
5.2
Contract no. HY/2009/19- Wan Chai Bypass Tunnal
(North Point Section) and Island Eastern Corridor Link
5.1.6. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.7. Two limit level exceedances were recorded on 5 and
5.1.8. Major
traffic noise observed during monitoring on 5 and
5.1.9. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring results and graphical presentation can
be referred in Appendix 5.2.
Contract no.
HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
5.2.1 As the land-based piling
and filling works- DP3 at Tin Hau had been completed on
5.2.2 The real-time noise
monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to
City Garden Electric Centre (RTN2a- Electric Centre) on
5.2.3 The major work activities
for Contract no. HY/2009/11 was confirmed substantial complete by RSS on
5.2.4 Limit
level exceedances were recorded at RTN2a-Electric Centre during daytime on
5.2.5 Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced
external wall renovation since
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitfield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since
l
RTN1 monitoring had been finished on
5.2.6
Details of real time noise monitoring results
and graphical presentation can be referred to Appendix 5.5.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.1. Air
monitoring was commenced on
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
5.3.1 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.2. Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations are
summarized in Table 5.8 below. No exceedance was
recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.3. Air
monitoring was commenced on
Table
5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site
Office |
5.3.2 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract
no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.4. The
proposed division of air monitoring stations are summarized in Table 5.10
below. No exceedance was recorded in the reporting month.
Table 5.10 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site
Office |
CMA2a |
|
5.3.3
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix
5.3.
5.4.1. As advised by WDII RSS, the pump station for WSD21 pump house relocation was implemented with respect to HK/2009/02 since
5.4.2. According to CWB RSS, oil dispersion at the culvert outfall
location at SW corner of CBTS was observed on 6, 22, 24 and 28 Feb 2014. An ICC
case (ICC ref: 2-92821253) regarding the above issue was lodged by CWB RSS team
to request for follow-up action by relevant departments.
5.4.3. Another oil dispersion at the culvert outfall location at
Ex-Cargo handling area was observed on
5.4.4. Water quality monitoring station RW21-P789 has been
implemented with respect to HK/2009/02 started on
5.4.5.
With respect
to status of cooling intakes relocation, WQM events on
5.4.6.
WDII/RSS advised that the dredging works for submarine pipeline at
5.4.7.
Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no
water deterioration with respect to NPR was commenced since 7 Jan 2012 and it
was completed on 6 February 2012.
5.4.8.
Water quality monitoring at WSD10 and WSD15 was temporary suspended
while water quality monitoring at WSD9 and WSD17 was implemented with respect
to HK/2009/02 from 8 Feb 12 onwards;
5.4.9.
Due to the marine piling under Contract no. HY/2009/19 was completed on
4 March 2013, the temporary suspension of impact water quality monitoring at C8
and C9 from 4 March 2013 have been monitored for 4-week period after the
completion of marine works to confirm no water deterioration.
5.4.10.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) since 3 Feb 2012,
there is a fine adjustment of the sampling location of water quality monitoring
at C9 to the closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.11. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
5.4.12. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.13. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
5.4.14.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
5.4.15.
As confirmed by CWB RSS, the marine pilling works under contract
HY/2009/19 was confirmed completed by
5.4.16.
With respect
to status of cooling intakes relocation, WQM events on
5.4.17.
Upon confirmation with WDII RSS and the IEC, water quality monitoring at
relocated intakes monitoring location P1, P3, P4 and P5 were commenced since
Table 5.11 Water Monitoring Stations for contracts
with respect to remaining DP3
work areas after the completion of DP5
& DP6 in 2012 and intake diversion in 2013
Contract No. |
Remaining DP3 and work area(s) |
Relevant Water Monitoring Stations, |
Division of WQM w.r.t tentative works commenced / to be commenced |
HK/2009/01 |
WCR3 |
C11 |
Apr 2013 |
HK/2009/02 |
WCR3, WCR4, TWCR4 |
RW21-P7891 |
Apr 2013 |
HK/2012/08 |
HKCEC2W, HKCEC2E |
WSD19, P13, P33, P43, P53 |
Aug 2013 |
HY/2009/15 |
TCBR2, TCBR3, TCBR1W, TPCWAE, TPCWAW |
C64, C7, Ex-WPCWA SW, Ex-WPCWA SE (plus enhanced DO monitoring
described in 4.6.3) |
Nov 2010 |
HY/2010/08 |
TCBR3, TCBR4 |
C64, C7 (plus enhanced DO monitoring described in 4.6.3) |
Mar 2014 |
Remarks:
-The water monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.
-4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring.
-Re-provisioned intake
reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5:
-Enhanced DO Monitoring at
C6 since the intake abandon in May 2011.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.18. Water
monitoring for Contract no. HK/2009/01 was commenced on
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
-
WSD7
and WSD20 water quality monitoring were temporarily suspended since
-
C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.19. Water
monitoring for Contract no. HK/2009/02 was commenced on
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
|
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from
-
C5e
and C5w water quality monitoring station was temporarily suspended since
Contract
no. HK/2012/08 - Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West
5.4.20.
Water monitoring for Contract no. HK/2012/08 was commenced on
Table 5.14 Water
Monitoring Stations for Contract no. HK/2012/08
Station
Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings ( |
835895.2 |
816215.2 |
|
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.21. As the removal of reclamation work
of TS1 at CBTS has been completed, all procedures have been rectified and
complied with the conditions set in EP-356/2009 and FEP-04/356/2009.
5.4.22.
Due to the commencement of the maintenance dredging on
5.4.23.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
Table
5.15 Water Monitoring
Stations for Contract no. HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation
for C6 was confirmed on
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
5.4.24. Due to the
commencement of the marine bored piling on
5.4.26.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Center (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
5.4.27.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.28.
As per the meeting with the representative of Excelsior Hotel and World
Trade Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from
5.4.29.
24 hours
monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on
5.4.30. Water
monitoring results measured in this reporting period are reviewed and
summarized. Details of water quality monitoring results and graphical
presentation can be referred in Appendix
5.4.
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
|
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
||
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
||
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
||
HK/2009/02 Monitoring started
on |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started
on |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 & HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
5 |
0 |
1 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on
-
WSD9 and WSD17 were implemented with respect to HK/2009/02 from
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on
- C8 and C9 were
implemented with respect to HY/2009/19 from
- C8
& C9 was temporary suspended on
- WSD7 and WSD20 were
temporarily suspended from
- C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
- C5e
and C5w water quality monitoring station was temporarily suspended since
5.4.31. Investigation
found that the exceedances were not project-related. The details of the
recorded exceedances can be referred to the Section 6.4.
5.4.32.
Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon
Shelter and Ex-Public Cargo Works Area was conducted three days per week during
the reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 5.18.
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
2 |
0 |
2 |
|
Ex-WPCWA SE |
0 |
2 |
0 |
2 |
|
Total |
0 |
4 |
0 |
4 |
5.4.33.
There were no action level exceedances and 8 limit level exceedances of
enhanced dissolved oxygen recorded in this reporting month. Investigation found
that the exceedances are not related to the Project works. The details of the
recorded exceedances can be referred to the Section 6.4.
5.4.34.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored. Details of additional DO monitoring results
can be referred in Appendix 5.4a.
5.4.35.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.5.1. Inert
C&D waste was disposed and non- inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
32.9 |
53192.755 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
0 |
10104.5 |
N/A |
Non-inert C&D materials disposed, m3 |
28.14 |
1609.21 |
|
Non-inert C&D materials recycled, kg |
0 |
151143 |
N/A |
Chemical waste disposed, kg |
0 |
10250 |
N/A |
*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3
¡V Special Treatment / Disposal contained in Geosynthetic Containers |
0 (Bulk Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
5.5.2. There were
no marine sediment Type 1- Open Sea Disposal and no marine sediments Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in this
reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
5.5.3. Inert
C&D waste and Non-inert C&D waste were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table
5.20 Details of
Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
3129.7 |
256785.48 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
49.45 |
1373.823 |
SENT Landfill |
Non-inert C&D materials recycled,
m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
0 |
11536 |
SENT Landfill |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
184167 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 |
129320 (Bulk volume) |
East of Sha Chau |
5.5.4. There are no
marine Sediment Type1- Open Sea Disposal and there are no Type 1 ¡V Open Sea
Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal was disposed
of in this reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
5.5.5. No Inert
C&D waste and no non- inert C&D waste were disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.21
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
304 |
ex-PCWA |
NIL |
111.9 |
TS4 |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal),
m3 |
0 (Bulk Volume) |
100208 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine
Disposal) , m3 |
0 (Bulk Volume) |
226495 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 2 ¡V Confined Marine Disposal), m3 |
12980 (Bulk Volume) |
22330 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
2760 |
11540 (Bulk Volume) |
East
of Sha Chau |
5.5.6. There were
marine sediment Type 2 ¡V
Confined Marine Disposal and marine sediment Type 3 ¡V Special Treatment / Disposal contained
in Geosynthetic Containers was
disposed of in this reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
5.5.7. No inert C&D
waste was disposed and no non-Inert C&D waste was recycled in this
reporting month. Details of the waste flow table are summarized in Table
5.22.
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
12567.88 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
267 |
HK/2009/01 |
Non-inert C&D materials disposed, m3 |
0 |
369.48 |
SENT/TKO137SF |
Non-inert C&D materials recycled, T |
0 |
60.58 |
Recyclers |
Chemical waste disposed, L |
0 |
2600 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
3,891 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
12,586 (Bulk Volume) |
|
5.5.8. There were
no marine sediments Type1- Open Sea Disposal and no Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal was deposed of in this
reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.5.9. Inert
C&D waste was disposed and non-inert C&D waste were disposed and
recycled in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
3147.6 |
339978.66 |
TM38 |
Inert C&D materials recycled, m3 |
0 |
53707.97 |
N/A |
Non-inert C&D materials disposed, m3 |
40.30 |
647.22 |
N/A |
Non-inert C&D materials recycled, kg |
11.59 |
320.82 |
N/A |
Chemical waste disposed, L |
0.35 |
1.63 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
162 |
South Cheung Chau |
Marine Sediment (Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
681 |
|
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
4976.00 |
|
5.5.10. There was no
marine sediment Type1- Open Sea Disposal and there was no Type 1 ¡V Open Sea
Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal generated
were disposed in this reporting month.
Contract no. HK/2012/08 ¡VWan Chai Development Phase
II ¡V Central- Wan Chai Bypass at Wan Chai West
5.5.11. Inert
C&D waste was disposed and no non-inert C&D waste were disposed in this
reporting month. Details of the waste flow table are summarized in Table
5.24.
Table 5.24 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal /
Dumping Grounds |
Inert C&D materials disposed, m3 |
51 |
1226 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
0 |
20 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal),
m3 |
0 |
31035 |
South of Cheung
Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
108155 |
South of The
Brothers (from |
5.5.12. There was
no marine sediment Type 1 ¡V Open Sea Disposa was disposed in this reporting
month.
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)
5.5.13. No Inert
C&D waste and non-inert C&D waste were disposed in this reporting
month. Details of the waste flow table are summarized in Table 5.25
Table 5.25 Details of Waste Disposal for Contract no. HY/2010/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal /
Dumping Grounds |
Inert C&D materials disposed, m3 |
Nil |
Nil |
N/A |
Inert C&D materials recycled, m3 |
NIl |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Dumping Permit (Type 1 ¡V |
0 |
12860 |
South Cheung Chau |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
0 |
17820 |
|
5.5.14. There was no
marine sediment Type 1 ¡V Open Sea Disposa and no Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal generated were
disposed in this reporting month.
6.0.1. The Event
Action Plan for construction noise, air quality and water quality are presented
in Appendix 6.1.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.1.1 No
exceedance was recorded in the reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.2 No
exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.1.3 No
exceedance was recorded in the reporting month.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.1.4
No exceedance was recorded in the reporting
month.
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
6.1.5
Two limit level
exceedances were recorded on 5 and
6.2.1 Limit
level exceedances were recorded at RTN2a-Electric Centre during daytime on
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.3.1 No
exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.3.2 No
exceedance was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.3.3 No
exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.4.1 There were
turbidity and SS exceedance recorded at C1, P1, P3 and P5 on
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
6.4.2 There were
occasionally turbidity exceedances at WSD21 on 7 and
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.4.3 There were
occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this
reporting month on 19, 21 24 and 26 March 2014. No odour nuisance was noted
during DO monitoring. After checking with Contractor, there was no marine work
undertaken on b19, 24 and
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.4 No
exceedance was recorded in this reporting month.
Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.4.5 No
exceedance was recorded in this reporting month.
Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West
6.4.6 There were
turbidity and SS exceedance recorded at C1, P1, P3 and P5 on
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip
Road 8)
6.4.7 No
exceedance was recorded in this reporting month.
6.5.2 No
project-related non-compliance from monitoring was recorded in the reporting
month.
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.3. According
to the construction programme of Central-Wanchai Bypass at Wanchai West at the
Central Reclamation Phase III area, Diaphragm wall construction, Guide wall
construction and culvert diversion were performed in March 2014 reporting
month. As no exceedances were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as
insignificant.
7.0.4. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II were marine works at HKCEC areas,
cross-harbour Watermains, Fresh Watermains and Cooling Watermains
Installations, tunnel works at Wan Chai East and filling works at Wan Chai
West. The major construction activities under Central-Wan Chai Bypass and
Island Eastern Corridor Link Projects were tunnel construction at TS4
and tunnel construction and dismantling of struts at TPCWAE. Bridge
construction and tunnel works at Central Interchange, ELS, segment launching
works and tunnel works at North Point area. The major environmental impact was
water quality impact at
7.0.5. The major
environmental impacts generated from tunnel works at Central and tunnel works
at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the
reporting month.. As no project related exceedance was recorded in the Project,
it was considered no adverse environmental impact caused by the Project works.
Thus, it is evaluated the cumulative construction impact was insignificant.
8.0.1. During
this reporting month, weekly environmental site audits were conducted for
Contracts no. HK/2009/01,
HK/2009/02, HY/2009/15, HK/2010/06, HY/2009/19, HK/2012/08 and HY/2010/08. No
non-conformance was identified during the site audits.
8.0.2. Four site
inspections for Contract no. HK/2009/01 was carried out on 5, 12, 20 and 26 March 2014 in reporting
month. Results of these inspections and outcomes are summarized in Table
8.1.
9.
Table
8.1 Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
140305_01 |
|
Noise
emission label should be provided to the air compressor ( Bay 8 & 9) |
Noise
label was provided |
Completion
as observed on |
140312_01 |
|
Public
drainage should be cleared more frequently preventing accumulation of mud (
Expo Drive Centre) |
The
public drainage was cleared properly |
Completion
as observed on |
140320_01 |
|
Effluent
should be properly treated prior to discharge ( Water Channel ) |
Properly
measure was provided for the effluent |
Completion
as observed on |
140320_02 |
|
Floating
refuse should be cleaned more frequently ( Bay 8 & 9 ) |
Floating
refuse was cleaned |
Completion
as observed on |
140326_01 |
|
Properly
measure should be provided as to reduce noise generated from breaking works (
Bay 8 & 9 ) |
The
machinery was removed. |
Completion
as observed on |
9.0.1. Four site
inspections for Contract no. HK/2009/02 was carried out on 6, 13, 19 and 27 March
2014 in reporting month. Results of these inspections and outcomes are
summarized in Table 8.2.
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
140327_01 |
|
Provide
3- sides and top cover to grouting station ( WCR2) |
3-sides
and top cover was provided to grounting station. |
Completion as
observed on3 April 2014 |
9.0.2.
Four site inspections for Contract no.
HY/2009/15 was carried out on 4, 11, 18 and 25 February 2014 in reporting month.
The results of these inspections and outcomes are summarized in Table
8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by
Contractor |
Outcome |
|
140311_04 |
|
Provide drip tray to chemical waste container
and provide plug to drip tray to prevent leakage |
Drip trays were provided |
Completion as observed on |
140311_02 |
|
Leaked oil should be collected as chemical
waste |
Leaked oil was cleared as chemical waste. |
Completion as observed on |
140311_04 |
|
Mud resting at the edge of seawall should be
cleared to prevent drop off |
Mud resting at the edge of seawall have been
removed. |
Completion as observed on |
140318_01 |
|
Provide maintenance to PME to prevent oil
leakage and leaked oil shall be cleared as chemical waste (TS4/TS2) |
no further leakage was observed and leaked
oil was cleared as chemical waste |
Completion as observed on |
140318_02 |
|
Provide waste collection point and collect
refuse to prevent wind blown waste (TS2) |
Refuses were collected and waste collection
bags were provided |
Completion as observed on |
140325_01 |
|
Tighten the silt curtain to avoid gap during
rock placing works |
The condition of silt curtain was improved |
Completion as observed on |
9.0.3. Four site
inspections for Contract no. HK/2010/06 was carried out on 3, 10, 20 and 24 March
2014 in reporting month. The results of these inspections and outcomes are
summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
140320_01 |
|
Floating refuse
should be cleaned more frequently ( Top of precast Unit) |
Floatinf refuse was
removed |
Completion as
observed on |
9.0.4.
Four site inspections for Contract no.
HY/2009/19 was carried out on 5, 12, 20 and 26 March 2014 in reporting month. The
results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2009/19
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
140305_01 |
|
Improve the cleaning of public road near exit
to prevent mud deposit and wheel wash runoff |
The public road near exit was cleaned |
Completion as observed on |
9.0.5.
Four site inspections for Contract no.
HK/2012/08 was carried out on 4, 11, 18 and 26 March 2014 in this reporting period. No particular finding was observed in
this reporting month.
9.0.6. Four site
inspections for Contract no. HY/2010/08 was carried out on 6, 13, 20 and 27
March 2014 in this reporting period. No particular finding was observed in this
reporting month.
9.0.1. No
environmental complaint was received in the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
28 |
March 2014 |
0 |
|
|
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
WDII/RSS advised that the dredging works for submarine pipeline at
10.0.3.
As the land-based piling and filling works- DP3 at Tin Hau had been
completed on
10.0.4.
The real-time noise monitoring at RTN2-Oil Street
Community Liaison Centre has been relocated to City Garden Electric Centre
(RTN2a- Electric Centre) on
10.0.5.
Water quality monitoring at WSD10 and WSD15 will be temporary suspended
while water quality monitoring at WSD9 and WSD17 were implemented with respect
to HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.6.
Due to the marine piling under Contract no. HY/2009/19 was completed on
4 March 2013, the temporary suspension of impact water quality monitoring at C8
and C9 from 4 March 2013 have been monitored for 4-week period after the
completion of marine works to confirm no water deterioration.
10.0.7. Water
quality monitoring at C8 & C9 was temporary suspended on
10.0.8.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
10.0.9.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.10. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3, 11, 13,
15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
10.0.11. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.12. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
¡P
Diversion of traffic from ¡P
Installation of pre-bored H-piles. Meanwhile in
the reclaimed area in stage 3, plant mobilization (e.g. piling rig) at the
area adjacent to the temp road after road diversion. ¡P
Stage 1 tunnel excavation work further down to
-10 mPD. Bay 6 blinding layer. The ¡P
overall Stage 1 tunnel structure works. ¡P
Stage 2 construction of Dwall at Water Channel
south side ¡P
Cooling mainlaying works for BI, BG & BF
along ¡P
Trimming works at Fairway and the target. ¡P
Tree transplanting works at Tsim Sha Tsui planter
area near HK Culture Centre. |
¡P
To conform the installation and setting as in
the silt screen deployment plan ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To cover the dusty material or stockpile by
impervious sheet ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
To well maintain
the mechanical equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant
that may be in intermittent use should be shut down between work periods or
should be throttled down to a minimum ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HK/2009/02 |
Sections IVA, IVB & IVC: ¡P
All outstanding works for handing over P7, P8 and
P9 Cooling Water Pumping Stations including the 8x8 pit and the adjacent
cable relocation to their permanent location. Section V: ¡P
Capping the existing DN600 salt watermains at ¡P
All outstanding ABWF works at WSD Salt Water
Pumping Station. Section VII: ¡P
Backfilling works for Section VIIIA & VIIIB: ¡P
All plumbing system including the connection with
the existing water supplies system in order to secure the Water Certificate
(WWO46) from WSD. ¡P
ABWF works at 1/F and 2/F of Ferry Pier and ready
for handing over it to Star Ferry for commencing their fitting-out works. ¡P
Installation of fender system. ¡P
Testing & commissioning of both movable ramps
and disabled lift for subsequent handing over to Star Ferry. ¡P
Installation of seating base plates and steel
frames and roof canopy cladding installation. Section XI: ¡P
Removal of existing E&M equipment at the
abandoned SHK Cooling Water Pump House. ¡P
Advanced dredging works of WCR3 by night work |
¡P
To cover the dusty material or stockpile by
impervious sheet; ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment
plan ¡P
Movable noise
barrier shall be deployed for demolition works ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Review silt screen
deployment and silt curtain deployment and resubmit associate
plans to EPD ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HY/2009/15 |
¡P
Construction of EVA |
¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HK/2010/06 |
¡P
Nil |
¡P
To conform the installation and setting as in
the silt screen and silt curtain
deployment plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2009/19 |
¡P
Removal of strut at ELS ¡P
Removal of marine platform ¡P
Construction of Dolphin Cap ¡P
ELS, EVB and Cut & Cover Tunnel ¡P
Laying of 1500f pipe ¡P
Launching of segments ¡P
Extraction of temporary pile from marine section ¡P
Construction of bridge TA1 ¡P
Pre-bored H-pile for Admin. Building ¡P
U-beam installation ¡P
Parapet ¡P
Wing slab extension for segment |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment plan |
HK/2012/08 |
¡P
ELS for box culvert La at ¡P
Filling for seawall rock mound formation ¡P
Filling for reclamation ¡P
Works for abandoning submarine sewerage outfall
and watermain ¡P
Installation of caisson seawall unit |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2010/08 |
¡P
Nil |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |